On July 13, Mayor Doug Wilson opened the floor at Kannapolis City Hall for public comment on a $40 million general obligation bond for parks. No one came forward to speak for or against it. The council then voted unanimously to put the question on the November ballot.
The silent hearing stands out against the spring. In March and April, residents kept coming to council meetings to talk about one park in particular. The bond Kannapolis voters will see on November 3 is the city's answer to those meetings. It also changes how the decision gets made. A project the council set aside during budget season now goes to a direct citywide vote, along with five others.
The park that kept coming back
Eastside Park has been in the works since 2017. That year the city bought the property on Midlake, which fronts Lake Fisher. The city's August 28 announcement gives the address as 1100 Midlake Avenue. The council approved a plan in 2019 that called for lakefront walking and biking trails, small- and large-dog areas, a splash pad, a playground, paddleboats, picnic shelters and open space. A pollinator garden and an osprey platform were also floated.
The plan then stalled. At its February 2026 retreat, the council talked about returning a $500,000 grant from the N.C. Parks and Recreation Trust Fund that had been awarded toward the park's $5.2 million cost. The project was not on the short list of capital priorities for the coming budget.
Residents spoke up at the next several meetings. Former Mayor Darrell Hinnant warned that a returned grant could hurt the city's chances with that agency later. He suggested the council reconsider a $2 million commitment for a history museum in the former Wells Fargo building on West Avenue. Debbie Vavra called the park "already overdue," according to the Salisbury Post. At the April 13 meeting, Sophia Wilkerson said the east side has "nowhere to walk that's safe." Phil Goodman backed the council's approach and said the city was in better shape than it had been in 15 to 20 years.
Councilmember Isaiah Payne summed up where the council stood that night:
"We did not say 'no' to Eastside park. We just said 'not right now.' The $500,000 is less than 10 percent of the overall cost."
Four weeks later, on May 11, the council unanimously approved a notice of intent to pursue the bond. According to the city, the Eastside property has been purchased and its master plan finished, and the $500,000 grant is listed as an offset to the park's cost.
Eastside is one of six projects in the bond
Kannapolis has never issued a general obligation bond. The city also says it has not built a traditional park or new athletic fields in more than 20 years. It says the priority list came from several years of surveys and community meetings. Here is what the $40 million would cover, based on the city's August 28 announcement:
| Project | Location | What's planned |
|---|---|---|
| Eastside Park | 1100 Midlake Avenue, 33 acres on Lake Fisher | Dog park, splash pad, walking trail, fitness stations, restrooms, paddleboats, picnic shelters, playground |
| Westside Park | Davidson-Concord Road / NC 73, 55 acres | Playgrounds, Rocky River Greenway access, softball and baseball fields, multi-use fields for soccer, football and lacrosse, restrooms, picnic shelters |
| Glenn Avenue Park | 76-acre site | Athletic fields and passive park features |
| Irish Buffalo Creek Greenway, Phase 2 | Rogers Lake Road to Highway 3 | About one mile of greenway |
| Irish Buffalo Creek Greenway, Phase 3 | Highway 3 to Pine Street near Fred L. Wilson Elementary | About three-quarters of a mile |
| Rocky River Greenway | From the Shiloh Church Road parking lot | West toward the Mecklenburg County line, and south from the current stub to the Highway 73 bridge |
| Gem Theatre, Phase 3 | Downtown Kannapolis | Expanded concessions and lobby, second-floor improvements |
The greenway pieces extend trails people already use. Irish Buffalo Creek Greenway Phase One opened in 2021, and the city's project tracker has listed Phase Two as in planning. The bond would pay for Phases 2 and 3 together, about 1.75 miles in all. The city has a separate $245,000 grant toward the Irish Buffalo Creek work.
The Gem Theatre item finishes a renovation that is already well along. The city bought the theater in 2015. In 2021 it replaced the roof and HVAC, renovated the marquee and added first-floor restrooms. An interior renovation, estimated at about $1.2 million, followed. It started in December 2023 and the theater reopened May 16, 2024 with new seats, a refinished stage, a new screen and projector, and repaired original plaster. Phase 3 would take on the lobby, the concession stand and the second floor.
Putting all six projects into one question means voters approve or reject them as a set. The ballot does not list the projects separately. The question authorizes $40,000,000 for "acquiring, constructing, renovating and improving parks and recreation facilities, including, without limitation, athletic fields, parks, playgrounds, greenways, and open space." According to the city's FAQ, if the bond fails, the proposed projects would not move forward "at this time."
What the tax figure means, in the right units
Some city materials describe the possible tax increase as "$0.046 cents." The city's formal notice gives the precise version, a property tax increase of $0.046 per $100 of assessed value, which works out to $46 per $100,000. At that full rate, a home assessed at $300,000 would carry $138 a year, or $11.50 a month. That figure is simple arithmetic from the notice. The city has not published it as an example.
The full rate assumes all $40 million is borrowed. At the July 13 hearing, Assistant City Manager Tina Cline said approval would not raise the tax rate right away. Any increase would track the amount borrowed at the time. "If you borrow $10 million, your tax rate would be based on $10 million for however long until the next project is begun," she said. Parks and Recreation Director Gary Mills put numbers on it. Borrowing $10 million would cost the average household about $2.87 a month, compared with more than $11 if the full $40 million were borrowed at once. Mills also said an increase would not be needed if the council can repay within the existing budget.
According to the city's FAQ, Kannapolis could draw on the bond over seven years. The city's announcement says construction would be staggered and finished within ten years. No public material lists which project would be built first. The ballot puts estimated total repayment at $62,444,800, which is $40 million in principal plus $22,444,800 in interest. In May, city projections put project costs near $37.5 million, with $2.5 million held as contingency. At its June 22 meeting, the council discussed lowering the request to $38 million but did not adopt the change.
The staging matters for Eastside Park. In April it competed for space in a single year's budget and lost. Under the bond, the council would decide when to borrow for each project over several years, and each draw would carry its own rate impact. That is the real change in how Kannapolis would pay for parks.
When and where to vote
The full ballot language appears in Rowan County's official election document, and Kannapolis residents on the Rowan side of the city vote through Rowan County. The dates and sites below are Cabarrus County's. You can vote early at any of these four sites, two of them in Kannapolis. On Election Day, you vote at your assigned precinct.
- Afton Ridge Library and Active Living Center, 6095 Glen Afton Blvd., Kannapolis
- Rowan-Cabarrus Community College at NCRC, 399 Biotechnology Lane, Kannapolis
- Cabarrus EMS HQ Station 9, 793 Cabarrus Ave. W., Concord
- Cabarrus Arena & Events Center, 4751 NC Hwy 49, Concord
Key dates for Cabarrus voters:
- October 9, 5 p.m.: registration deadline for Election Day
- October 15 to 31: early voting. Weekdays run 8 a.m. to 7:30 p.m. Saturdays October 17 and 24 run 8 a.m. to 5 p.m. The last day, Saturday, October 31, runs 8 a.m. to 3 p.m.
- October 20, 5 p.m.: deadline to request an absentee ballot
- November 3: Election Day
Cabarrus County voters will also see a separate county bond of up to $400 million for school systems and Rowan-Cabarrus Community College. The county's information sessions are about that measure, not the city parks bond. The city has posted project pages and an FAQ for the parks bond at kannapolisparksbond.com.
If you live near Lake Fisher, the Shiloh Church Road trailhead, or Irish Buffalo Creek and want to know how nearby park plans could affect your home's value, Kirk Hanson and the Coldwell Banker CK Select team can walk you through it. Request your home valuation, and we will put together a figure based on what is actually planned for your part of Kannapolis.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.